{"id":8172,"date":"2025-12-28T05:31:43","date_gmt":"2025-12-28T12:31:43","guid":{"rendered":"https:\/\/iconiccb.com\/?p=8172"},"modified":"2025-12-28T05:31:45","modified_gmt":"2025-12-28T12:31:45","slug":"seattle-kitchen-remodel-timeline-2026","status":"publish","type":"post","link":"https:\/\/iconiccb.com\/seattle-kitchen-remodel-timeline-2026\/","title":{"rendered":"Kitchen Remodel Timeline: What to Expect Week by Week (2026 Guide)"},"content":{"rendered":"\n<p>Picture this: the heart of your home, your kitchen, completely transformed. The old, outdated cabinets are gone. In their place? Sleek, custom cabinetry. Warm lighting reflects off freshly laid floors. The new layout flows effortlessly: open, modern, and designed for the way your family actually lives. It\u2019s everything you hoped for&#8230; <strong>but how long does it take to get from demo day to dinner party?&nbsp;<\/strong><\/p>\n\n\n\n<p>If you\u2019ve been thinking about remodeling your kitchen, you\u2019ve probably asked: <em>How long will this kitchen remodel really take?<\/em>And the truth is, the answer depends on a few key factors, from the size and scope of your project, to whether permits are involved, to most importantly, who you hire.<\/p>\n\n\n\n<p>In this <strong>2026 guide to Seattle kitchen remodel timelines<\/strong>, we\u2019ll walk you through what to expect week by week, how different project types impact your schedule, and where delays usually happen. We\u2019ll also explain how choosing the right partner, like Iconic Cabinetry, can make all the difference.<\/p>\n\n\n\n<p>Unlike traditional remodels that juggle separate designers, vendors, and contractors, Iconic\u2019s streamlined, all-in-one approach cuts out the chaos. With a full-service team, in-house showroom, and direct-sourced materials, we help Seattle homeowners move from planning to completion with fewer headaches and faster results.<\/p>\n\n\n\n<p>Let\u2019s break it all down.<\/p>\n\n\n\n<figure class=\"wp-block-image size-large\"><img fetchpriority=\"high\" decoding=\"async\" width=\"1024\" height=\"683\" src=\"https:\/\/iconiccb.com\/wp-content\/uploads\/2025\/12\/kitchen-timeline-seattle-1024x683.webp\" alt=\"Cozy farmhouse kitchen with wood island, brass pot rail, and woven pendant lighting\" class=\"wp-image-8176\" srcset=\"https:\/\/iconiccb.com\/wp-content\/uploads\/2025\/12\/kitchen-timeline-seattle-1024x683.webp 1024w, https:\/\/iconiccb.com\/wp-content\/uploads\/2025\/12\/kitchen-timeline-seattle-300x200.webp 300w, https:\/\/iconiccb.com\/wp-content\/uploads\/2025\/12\/kitchen-timeline-seattle-768x512.webp 768w, https:\/\/iconiccb.com\/wp-content\/uploads\/2025\/12\/kitchen-timeline-seattle.webp 1500w\" sizes=\"(max-width: 1024px) 100vw, 1024px\" \/><\/figure>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"timeline\">What\u2019s the Average Timeline for a Kitchen Remodel in Seattle?<\/h2>\n\n\n\n<p>While every project is unique, most kitchen renovations fall somewhere between <strong>6 to 12+ weeks<\/strong> from the start of construction to final walkthrough, but that number can shift based on the size, complexity, and whether structural or permitting elements are involved.<\/p>\n\n\n\n<h3 class=\"wp-block-heading\" id=\"minor\">Minor Updates: 6\u20138 Weeks<\/h3>\n\n\n\n<p>Think of cosmetic changes: cabinet refacing, new countertops, updated backsplash, lighting, or <a href=\"https:\/\/iconiccb.com\/flooring\">flooring<\/a>. These projects move quickly, especially when layout and plumbing stay the same.<\/p>\n\n\n\n<h3 class=\"wp-block-heading\" id=\"full-remodel\">Full Remodels: 10\u201314+ Weeks<\/h3>\n\n\n\n<p>This is the most common scenario for homeowners in Seattle suburbs like Lynnwood, Issaquah, or Shoreline. It involves removing existing cabinetry and fixtures, upgrading systems (electrical, plumbing), and installing new custom cabinetry, surfaces, and appliances. Layout changes or aging infrastructure can add time.<\/p>\n\n\n\n<h3 class=\"wp-block-heading\" id=\"structural\">Custom or Structural Remodels: 14\u201320+ Weeks<\/h3>\n\n\n\n<p>If you&#8217;re relocating walls, moving the kitchen to a different part of the house, or integrating major structural work (like open-concept redesigns), expect a longer timeline. These projects often involve architectural drawings, engineering approvals, and multi-phase permits.<\/p>\n\n\n\n<h3 class=\"wp-block-heading\" id=\"what-else\">What Else Affects the Timeline?<\/h3>\n\n\n\n<p>The biggest wildcard? <strong>Permitting.<\/strong> In Seattle and surrounding cities, permits can add anywhere from <strong>2 to 6 weeks<\/strong>, especially if the project includes plumbing, electrical, or layout changes.&nbsp;<\/p>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"phase-by-phase\">Kitchen Remodel Timeline: Phase-by-Phase Breakdown<\/h2>\n\n\n\n<p>To better understand what actually happens during a remodel, and when, here\u2019s a look at the typical phases of a Seattle kitchen renovation. While every project has its own rhythm, most follow this general flow.<\/p>\n\n\n\n<p><strong><em>Keep in mind:<\/em><\/strong> Iconic Cabinetry\u2019s all-in-one model helps reduce downtime between these phases, thanks to in-house coordination, local sourcing, and efficient project management.<\/p>\n\n\n\n<figure class=\"wp-block-image size-large\"><img decoding=\"async\" width=\"1024\" height=\"664\" src=\"https:\/\/iconiccb.com\/wp-content\/uploads\/2025\/12\/kitchen-remodel-in-shoreline-1024x664.webp\" alt=\"Rustic kitchen with exposed stone backsplash, wood shelf, and pantry jars in a natural-toned remodel design\" class=\"wp-image-8175\" srcset=\"https:\/\/iconiccb.com\/wp-content\/uploads\/2025\/12\/kitchen-remodel-in-shoreline-1024x664.webp 1024w, https:\/\/iconiccb.com\/wp-content\/uploads\/2025\/12\/kitchen-remodel-in-shoreline-300x194.webp 300w, https:\/\/iconiccb.com\/wp-content\/uploads\/2025\/12\/kitchen-remodel-in-shoreline-768x498.webp 768w, https:\/\/iconiccb.com\/wp-content\/uploads\/2025\/12\/kitchen-remodel-in-shoreline.webp 1500w\" sizes=\"(max-width: 1024px) 100vw, 1024px\" \/><\/figure>\n\n\n\n<figure class=\"wp-block-table\"><table class=\"has-fixed-layout\"><tbody><tr><td><strong>Phase<\/strong><\/td><td><strong>Estimated Duration<\/strong><\/td><td><strong>What Happens During This Phase<\/strong><\/td><\/tr><tr><td><strong>1. Planning &amp; Design<\/strong><\/td><td>2\u20134 weeks<\/td><td>Initial consultation, site measurements, layout planning, and material selection. Iconic clients visit our showroom and work with our in-house designers to finalize details.<\/td><\/tr><tr><td><strong>2. Permitting<\/strong> <em>(if required)<\/em><\/td><td>2\u20136 weeks<\/td><td>If the remodel involves plumbing, electrical, or structural changes, permits must be submitted and approved through your local city (e.g. Seattle, Shoreline, Issaquah). Iconic handles this for you.<\/td><\/tr><tr><td><strong>3. Demolition<\/strong><\/td><td>3\u20135 days<\/td><td>Removal of old cabinets, appliances, flooring, and fixtures. Site prep and dust protection included.<\/td><\/tr><tr><td><strong>4. Structural &amp; Rough-In Work<\/strong><\/td><td>1\u20132 weeks<\/td><td>Framing (if needed), plus rough plumbing, HVAC, and electrical. City inspections may happen during this stage.<\/td><\/tr><tr><td><strong>5. Installation<\/strong><\/td><td>2\u20133 weeks<\/td><td>New cabinetry, flooring, lighting, countertops, and appliances are installed. This is when the kitchen takes shape.<\/td><\/tr><tr><td><strong>6. Finishing Touches<\/strong><\/td><td>1 week<\/td><td>Backsplash, paint, hardware, trim work, and any final tweaks. Final inspections (if required) also happen here.<\/td><\/tr><tr><td><strong>Total Time Range<\/strong><\/td><td>6\u201312+ weeks<\/td><td>Iconic helps keep projects on track by managing each step under one roof.<\/td><\/tr><\/tbody><\/table><\/figure>\n\n\n\n<p><strong>Want more detail?<\/strong> You can always <a href=\"https:\/\/iconiccb.com\/faq\/\">check our FAQ<\/a> or talk to a project specialist to get a personalized estimate based on your home and goals.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"scope\">Project Scope: Minor vs. Major Kitchen Remodel Timelines<\/h2>\n\n\n\n<p>While the timeline phases follow a fairly standard flow (as we showed above), your actual remodel timeline depends heavily on the size of your project.<\/p>\n\n\n\n<p>Not all kitchen remodels are created equal, and neither are their timelines. One of the biggest factors that determines how long your remodel will take (and how much it might cost) is the <strong>scope of work<\/strong>. Let\u2019s break it down:<\/p>\n\n\n\n<h3 class=\"wp-block-heading\" id=\"minor-scope\">Minor Remodel (6\u20138 weeks)<\/h3>\n\n\n\n<p>This is a cosmetic refresh, ideal if your layout works but the space feels dated.<\/p>\n\n\n\n<p><strong>Typical features include:<\/strong><\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li>Painting or refinishing cabinets<\/li>\n\n\n\n<li>Replacing countertops or backsplash<\/li>\n\n\n\n<li>New cabinet hardware<\/li>\n\n\n\n<li>Swapping in modern lighting and plumbing fixtures<\/li>\n<\/ul>\n\n\n\n<p>For minor remodels, <strong>$10,000 might be enough<\/strong>, especially if you\u2019re not relocating appliances or changing the layout. However, that budget requires smart material choices and little to no structural work.<\/p>\n\n\n\n<h3 class=\"wp-block-heading\" id=\"mid-range\">Mid-Range Remodel (8\u201312 weeks)<\/h3>\n\n\n\n<p>This is where we start making more meaningful updates.<\/p>\n\n\n\n<p><strong>Usually includes:<\/strong><\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li>Replacing cabinetry (stock or semi-custom)<\/li>\n\n\n\n<li>New flooring, countertops, and lighting<\/li>\n\n\n\n<li>Minor layout changes (e.g., removing a peninsula or shifting appliance locations)<\/li>\n<\/ul>\n\n\n\n<p><strong>$10K likely won\u2019t cover<\/strong> a mid-range remodel, especially in the Seattle area. Average ranges here start closer to <strong>$30,000\u2013$50,000<\/strong>, depending on finishes and layout complexity.<\/p>\n\n\n\n<figure class=\"wp-block-image size-large\"><img decoding=\"async\" width=\"1024\" height=\"684\" src=\"https:\/\/iconiccb.com\/wp-content\/uploads\/2025\/12\/blue-kitchen-1024x684.webp\" alt=\"Small kitchen remodel with blue cabinets, butcher block countertop, and espresso machine station\" class=\"wp-image-8174\" srcset=\"https:\/\/iconiccb.com\/wp-content\/uploads\/2025\/12\/blue-kitchen-1024x684.webp 1024w, https:\/\/iconiccb.com\/wp-content\/uploads\/2025\/12\/blue-kitchen-300x200.webp 300w, https:\/\/iconiccb.com\/wp-content\/uploads\/2025\/12\/blue-kitchen-768x513.webp 768w, https:\/\/iconiccb.com\/wp-content\/uploads\/2025\/12\/blue-kitchen.webp 1500w\" sizes=\"(max-width: 1024px) 100vw, 1024px\" \/><\/figure>\n\n\n\n<h3 class=\"wp-block-heading\" id=\"full-gut\">Full Gut or Custom Remodel (12\u201320+ weeks)<\/h3>\n\n\n\n<p>The full transformation, down to the studs and rebuilt to match your dream vision.<\/p>\n\n\n\n<p><strong>These remodels often involve:<\/strong><\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li>Full demolition<\/li>\n\n\n\n<li>Structural work (removing or adding walls)<\/li>\n\n\n\n<li>New plumbing, electrical, and HVAC systems<\/li>\n\n\n\n<li>Custom cabinetry and high-end finishes<\/li>\n\n\n\n<li>Layout reconfiguration and permitting<\/li>\n<\/ul>\n\n\n\n<p>This level of remodel requires a <strong>higher investment<\/strong>, typically <strong>$75,000\u2013$150,000+<\/strong> in the Seattle metro area. But the payoff is a kitchen tailored exactly to your lifestyle, with modern flow, storage, and resale value.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"plan-smart\">Planning Smart: How to Avoid Kitchen Remodel Delays<\/h2>\n\n\n\n<p>No one starts a kitchen remodel hoping it will drag on for months. But delays are common, and often preventable. Whether you&#8217;re in Seattle, Shoreline, or beyond, understanding the most frequent causes of hold-ups can help you plan smarter and finish faster.<\/p>\n\n\n\n<h3 class=\"wp-block-heading\" id=\"delay-causes\">Common Causes of Kitchen Remodel Delays<\/h3>\n\n\n\n<ul class=\"wp-block-list\">\n<li><strong>Scope Creep:<\/strong> Changing plans mid-project, like swapping materials or expanding the remodel, adds time and complexity.<\/li>\n\n\n\n<li><strong>Material Backorders:<\/strong> Some items (like custom cabinetry or specialty tiles) may have long lead times, especially if ordered late.<\/li>\n\n\n\n<li><strong>Disjointed Contractors:<\/strong> Working with separate designers, suppliers, and installers often creates bottlenecks when one schedule doesn&#8217;t align with the next.<\/li>\n<\/ul>\n\n\n\n<h3 class=\"wp-block-heading\" id=\"no-stress\">How to Remodel Without the Stress<\/h3>\n\n\n\n<p>The best way to avoid delays? <strong>Work with a one-stop partner<\/strong> like Iconic Cabinetry. Our integrated design-build process means:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li>You choose materials and finishes in one place at our showroom.<\/li>\n\n\n\n<li>Your project is managed by a single, local team.<\/li>\n\n\n\n<li>We coordinate every phase, reducing downtime between trades and approvals.<\/li>\n<\/ul>\n\n\n\n<h3 class=\"wp-block-heading\" id=\"tips\">Homeowner Tips to Stay on Track<\/h3>\n\n\n\n<ul class=\"wp-block-list\">\n<li><strong>Finalize all selections early.<\/strong> Cabinets, flooring, tile, fixtures: confirm your choices before demolition begins.<\/li>\n\n\n\n<li><strong>Approve designs quickly.<\/strong> Timely sign-offs on layouts and renderings help the project move forward smoothly.<\/li>\n\n\n\n<li><strong>Trust the process.<\/strong> Let your remodel team guide you through what\u2019s needed and when: experienced pros know how to avoid common pitfalls.<\/li>\n<\/ul>\n\n\n\n<p>If you&#8217;re starting to plan a remodel in Shoreline or nearby areas,<a href=\"https:\/\/iconiccb.com\/service-area\/shoreline\/\"> explore our local service page<\/a> to learn how we support homeowners from start to finish, without the typical remodel delays.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"faq\">Kitchen Remodel FAQs (Seattle Homeowners Ask Us This All the Time)<\/h2>\n\n\n\n<p>Have questions about kitchen remodeling in Seattle? You&#8217;re not alone. Below are the most common questions we hear, along with straightforward answers to help you feel confident moving forward.<\/p>\n\n\n<div id=\"rank-math-faq\" class=\"rank-math-block\">\n<div class=\"rank-math-list \">\n<div id=\"faq-question-1766924774658\" class=\"rank-math-list-item\">\n<h3 class=\"rank-math-question \">How long does a Seattle kitchen remodel usually take?<\/h3>\n<div class=\"rank-math-answer \">\n\n<p>Most projects take <strong>6 to 12+ weeks<\/strong>, depending on the size, scope, and whether permits are required. Minor remodels (cabinet refreshes, countertops) are usually on the shorter end, while full or structural renovations take longer. We break down each phase in this section or you can explore our <a href=\"https:\/\/iconiccb.com\/sitemap\/\">sitemap<\/a> to find more information.<\/p>\n\n<\/div>\n<\/div>\n<div id=\"faq-question-1766924783704\" class=\"rank-math-list-item\">\n<h3 class=\"rank-math-question \">What is the 3&#215;4 kitchen rule?<\/h3>\n<div class=\"rank-math-answer \">\n\n<p>The 3&#215;4 rule refers to a practical layout guideline: <strong>at least 3 feet of clearance around appliances<\/strong> and <strong>4 feet between countertops or islands<\/strong> for safe, comfortable movement. It helps ensure good traffic flow and avoids bottlenecks, especially important in smaller Seattle kitchens. Iconic\u2019s in-house designers help apply space planning best practices to every layout.<\/p>\n\n<\/div>\n<\/div>\n<div id=\"faq-question-1766924847830\" class=\"rank-math-list-item\">\n<h3 class=\"rank-math-question \">Is $10K enough for a kitchen remodel in Seattle?<\/h3>\n<div class=\"rank-math-answer \">\n\n<p>It depends on your goals. <strong>$10,000 may cover a very minor refresh<\/strong> (such as cabinet painting, new hardware, and updated lighting) but won\u2019t stretch far for full cabinetry replacements or layout changes. In Seattle, most kitchen remodels fall between <strong>$30,000 and $100,000+<\/strong>.\u00a0<\/p>\n\n<\/div>\n<\/div>\n<div id=\"faq-question-1766924852522\" class=\"rank-math-list-item\">\n<h3 class=\"rank-math-question \">How much does a kitchen remodel cost locally?<\/h3>\n<div class=\"rank-math-answer \">\n\n<p>Local costs vary based on materials, square footage, and scope, but typical ranges include:<br \/>&#8211; Minor: $10K\u2013$25K<br \/>&#8211; Mid-range: $30K\u2013$60K<br \/>&#8211; Full custom: $75K\u2013$150K+<br \/>We\u2019ll be covering this in detail in an upcoming blog post. Want an estimate now? Our team can provide a personalized quote based on your goals.<\/p>\n\n<\/div>\n<\/div>\n<div id=\"faq-question-1766924866586\" class=\"rank-math-list-item\">\n<h3 class=\"rank-math-question \">What makes the kitchen remodel process faster?<\/h3>\n<div class=\"rank-math-answer \">\n\n<p>Two words: <strong>coordination and clarity.<\/strong> Remodels move faster when:<br \/>-You finalize all materials and selections early<br \/>&#8211; One team handles everything., from design to install<br \/>&#8211; Permits are submitted quickly and correctly<br \/>That\u2019s why Iconic Cabinetry\u2019s all-in-one approach consistently reduces delays compared to the traditional \u201cdesign, bid, and build\u201d model.<\/p>\n\n<\/div>\n<\/div>\n<\/div>\n<\/div>\n\n\n<figure class=\"wp-block-image size-large\"><img loading=\"lazy\" decoding=\"async\" width=\"1024\" height=\"683\" src=\"https:\/\/iconiccb.com\/wp-content\/uploads\/2025\/12\/black-kitchen-remodel-issaquah-1024x683.webp\" alt=\"Modern black tile kitchen backsplash with open wood shelving and stainless steel range in a Seattle remodel\" class=\"wp-image-8173\" srcset=\"https:\/\/iconiccb.com\/wp-content\/uploads\/2025\/12\/black-kitchen-remodel-issaquah-1024x683.webp 1024w, https:\/\/iconiccb.com\/wp-content\/uploads\/2025\/12\/black-kitchen-remodel-issaquah-300x200.webp 300w, https:\/\/iconiccb.com\/wp-content\/uploads\/2025\/12\/black-kitchen-remodel-issaquah-768x512.webp 768w, https:\/\/iconiccb.com\/wp-content\/uploads\/2025\/12\/black-kitchen-remodel-issaquah.webp 1500w\" sizes=\"(max-width: 1024px) 100vw, 1024px\" \/><\/figure>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"why-iconic\"><strong>Why Iconic Cabinetry = Faster, Smarter Remodels<\/strong><\/h2>\n\n\n\n<p>When it comes to kitchen remodeling, most delays and frustrations come down to one thing: <strong>too many moving parts<\/strong>. Designers, vendors, subcontractors, city approvals, and you stuck in the middle.<\/p>\n\n\n\n<p>That\u2019s where <strong>Iconic Cabinetry\u2019s design-build model<\/strong> changes everything.<\/p>\n\n\n\n<h4 class=\"wp-block-heading\"><strong>What Makes Our Process Different?<\/strong><\/h4>\n\n\n\n<ul class=\"wp-block-list\">\n<li><strong>One team, under one roof.<\/strong> From initial design to final install, everything is handled by our in-house team. You\u2019re not chasing down multiple contractors or wondering who\u2019s responsible for what.<\/li>\n\n\n\n<li><strong>Direct material sourcing.<\/strong> We source cabinetry, flooring, and surfaces directly, cutting out supplier delays and inflated costs.<\/li>\n\n\n\n<li><strong>Local showroom experience.<\/strong> Visit our Lynnwood showroom to see, touch, and select materials.<\/li>\n\n\n\n<li><strong>Built for busy homeowners.<\/strong> Our approach is ideal for Seattle-area families who want a modern kitchen without managing 10 different vendors.<\/li>\n<\/ul>\n\n\n\n<p>Whether you&#8217;re planning a kitchen remodel in <a href=\"https:\/\/iconiccb.com\/service-area\/renton\/\">Renton<\/a>, Lynnwood, or another nearby city, our team keeps your project moving with a clear plan, responsive communication, and decades of experience in the local market.<\/p>\n\n\n\n<p>It\u2019s all part of our promise: a <strong>stress-free remodel process<\/strong> that delivers beautiful, lasting results, without the chaos.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"start-here\"><strong>Ready to Start Your Seattle Kitchen Remodel?<\/strong><\/h2>\n\n\n\n<p>You don\u2019t need to guess your way through timelines, costs, and contractor chaos. At Iconic Cabinetry, we make the process simple, from the first design sketch to final installation.<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li>One team handles it all<\/li>\n\n\n\n<li>Transparent pricing and timelines<\/li>\n\n\n\n<li>In-house showroom and direct sourcing<\/li>\n\n\n\n<li>Local, trusted experts serving Seattle and surrounding suburbs including <a href=\"https:\/\/iconiccb.com\/service-area\/issaquah\/\">Issaquah<\/a><\/li>\n<\/ul>\n\n\n\n<p>Whether you&#8217;re ready to dive in or just want to explore what\u2019s possible, we\u2019re here to help. <a href=\"#contact\"><strong>Book a free consultation<\/strong><\/a> or visit our Lynnwood showroom to see how easy remodeling can be when everything is under one roof.<\/p>\n\n\n\n<script type=\"application\/ld+json\">\n{\n  \"@context\": \"https:\/\/schema.org\",\n  \"@type\": \"Article\",\n  \"mainEntityOfPage\": {\n    \"@type\": \"WebPage\",\n    \"@id\": \"https:\/\/iconiccb.com\/seattle-kitchen-remodel-timeline-2026\"\n  },\n  \"headline\": \"Kitchen Remodel Timeline: What to Expect Week by Week (2026 Guide)\",\n  \"description\": \"Learn how long a Seattle kitchen remodel really takes. This 2026 guide from Iconic Cabinetry breaks down project scopes, phases, permitting, and ways to avoid delays.\",\n  \"image\": \"https:\/\/iconiccb.com\/wp-content\/uploads\/2025\/12\/shoreline-kitchen-remodel.webp\",\n  \"author\": {\n    \"@type\": \"Organization\",\n    \"name\": \"Iconic Cabinetry\"\n  },\n  \"publisher\": {\n    \"@type\": \"Organization\",\n    \"name\": \"Iconic Cabinetry\",\n    \"logo\": {\n      \"@type\": \"ImageObject\",\n      \"url\": \"https:\/\/iconiccb.com\/wp-content\/uploads\/2025\/06\/iconic-cabinetry-logo-e1750791075580-768x165.webp\"\n    }\n  },\n  \"datePublished\": \"2025-12-28T06:00:00-08:00\",\n  \"dateModified\": \"2025-12-28T06:00:00-08:00\"\n}\n<\/script>\n\n","protected":false},"excerpt":{"rendered":"<p>How long does a kitchen remodel take in Seattle? This 2026 guide breaks it down by phase, size, and scope, plus how permits and budgets affect your timeline.<\/p>\n","protected":false},"author":4,"featured_media":8177,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"footnotes":""},"categories":[27,67],"tags":[51,61,124],"class_list":["post-8172","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-remodel-planning","category-kitchen-remodeling","tag-kitchen-backsplash","tag-kitchen-remodeling","tag-timeline"],"acf":[],"_links":{"self":[{"href":"https:\/\/iconiccb.com\/wp-json\/wp\/v2\/posts\/8172","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/iconiccb.com\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/iconiccb.com\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/iconiccb.com\/wp-json\/wp\/v2\/users\/4"}],"replies":[{"embeddable":true,"href":"https:\/\/iconiccb.com\/wp-json\/wp\/v2\/comments?post=8172"}],"version-history":[{"count":4,"href":"https:\/\/iconiccb.com\/wp-json\/wp\/v2\/posts\/8172\/revisions"}],"predecessor-version":[{"id":8182,"href":"https:\/\/iconiccb.com\/wp-json\/wp\/v2\/posts\/8172\/revisions\/8182"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/iconiccb.com\/wp-json\/wp\/v2\/media\/8177"}],"wp:attachment":[{"href":"https:\/\/iconiccb.com\/wp-json\/wp\/v2\/media?parent=8172"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/iconiccb.com\/wp-json\/wp\/v2\/categories?post=8172"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/iconiccb.com\/wp-json\/wp\/v2\/tags?post=8172"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}